Project Information
Precinct
| 3 |
City
| San Antonio, District 10
|
Watershed
| Salado Creek
|
Creek
| Mud Creek
|
Project Type
| Low Water Crossing
|
Consultant:
RJ Rivera Associates, Inc.
Contractor:
Thyssen-Laughlin, Inc.
Construction Cost:
$3,231,869.00
Advertise:
October 2015
Construction Start:
July 2016
Construction End:
March 2019